WATERVILLE — The Ticonic Bridge spanning the Kennebec River between Waterville and Winslow will be closed completely to traffic and pedestrians the week of March 9-16. Cianbro Corp. of Pittsfield, which has the contract for the bridge, stated in a news release construction activities that week require access to the whole bridge.
Alternate routes include the Carter Memorial Bridge, which is south of the Ticonic Bridge, and the three bridges spanning the Kennebec between Fairfield and Benton, north of Waterville and Winslow.
Pedestrians may use the Two Cent Bridge just north of the Ticonic Bridge to cross the river between Waterville and Winslow as well as the Fairfield-Benton bridges.
On March 16, westbound vehicle traffic will be prohibited from the Ticonic Bridge, according to the Cianbro release. The bridge will reopen to eastbound traffic at 6 a.m. and access to the bridge will be allowed during the westbound detour.
The state Department of Transportation is replacing the U.S. Route 201 bridge as part of a $60 million project expected to be completed in May 2027. It is being replaced with a new, two-span steel girder with concrete bridge deck structure. Parts of the bridge were more than 100 years old when the work began in 2023.
We invite you to add your comments. We encourage a thoughtful exchange of ideas and information on this website. By joining the conversation, you are agreeing to our commenting policy and terms of use. More information is found on our FAQs. You can modify your screen name here.
Comments are managed by our staff during regular business hours Monday through Friday as well as limited hours on Saturday and Sunday. Comments held for moderation outside of those hours may take longer to approve.
Join the Conversation
Please sign into your CentralMaine.com account to participate in conversations below. If you do not have an account, you can register or subscribe. Questions? Please see our FAQs.