When Madison Paper Industries connected to central Maine’s first natural gas pipeline in April 2014, it was lauded as an achievement for both the mill and the pipeline company, estimated to bring both big cost savings and a reduced environmental impact to the area.

The Summit Natural Gas pipeline project did that, with the mill saving an estimated $5 million each year while its boilers run on natural gas to heat the mill facilities and dry paper.

But the energy savings weren’t enough to keep the mill open.

The natural gas that flows through the Summit pipeline makes up just a small part of the energy used by the Madison mill, which will close in May, laying off more than 200 workers.

With low electricity and gas prices this year, it’s “almost kind of tragic” to see manufacturers such as Madison Paper closing their doors when more natural gas is expected to flow to the area soon, said Patrick Woodcock, director of the governor’s energy office.

“Obviously there’s not just one factor that’s driving the competitiveness issues (with mills), but energy has been one of the main issues,” Woodcock said. “We are making progress with the pricing that we’re seeing now in some ways, but it was too late for a lot of them. It was the other market forces that were putting pressure on them, even though pricing right now is pretty decent.”

Advertisement

It takes about 350 million kilowatt hours — more than 32,000 times the amount used by an average household per year — of electricity to make the roughly 195,000 tons of paper the Madison mill produces annually. About 40 percent of the electricity needed to run the mill comes from the mill’s on-site hydropower facility, and a small amount is purchased from Madison Electric Works.

But most of the electricity that runs the mill is purchased from ISO New England, a regional electrical corporation that produces electricity via generators throughout New England. The electricity is purchased by customers such as Madison Paper at an hourly rate depending on demand. But the mill and others in New England have struggled to procure reliable electricity at affordable prices to the point that it has been a factor in temporary layoffs and shutdowns.

If there is low demand for electricity, prices are low because the bids are awarded to the lowest-cost generators, including those that run on natural gas. But when demand is high — such as on a cold winter day, when there is more demand for heat — there isn’t enough natural gas in New England to keep prices low. More bids are awarded to generators that run on higher-cost fuel sources such as oil or coal.

Last month, ISO New England said in a statement that electricity prices in New England were at nearly a 12-year low in 2015 because of low natural gas prices for most of the year. About 49 percent of the company’s electricity is produced from natural gas.

In June 2015, electricity prices at ISO New England were at their second-lowest since March 2003, at $19.61 per megawatt-hour, the statement said. Yet despite the overall low cost in 2015, February of that year featured some of the most expensive electricity costs at ISO New England, with an average cost of $126.70 per megawatt hour.

That was also around the time the Madison mill announced it would be issuing temporary layoffs for employees and ceasing production for a two-week period.

Advertisement

“We said, ‘No, we can’t turn the paper machine on and off depending on the hourly price of electricity,'” said Madison Paper Industries President and CEO Russ Drechsel. “So what we tried to do was pick the coldest times of the year and take the machine down for 16 to 18 days; so that’s how we operated in 2015.”

According to Drechsel, electricity prices were at times as high as $1,200 per megawatt hour in 2014. In 2016, prices have gone as high as $500 to $800 per megawatt hour.

EXPANDING CAPACITY

The Maritimes & Northeast Pipeline pumps natural gas from Canada through Maine, moving offshore gas from Nova Scotia’s Sable Island fields. Summit, distributing gas in the Kennebec Valley, is supplied off that main line, which stretches 346 miles in the U.S. down to Greater Boston.

Efforts are underway to expand pipeline capacity in New England, including two projects by Spectra Energy, the Algonquin Incremental Market project and the Atlantic Bridge Project, which are expected to bring more natural gas into New England and Canada. Spectra owns the bulk — 78 percent — of the Maritimes pipeline.

Construction began last year on the first major natural gas pipeline expansion designed to ease a bottleneck that’s keeping more gas from the Marcellus Shale deposits in Pennsylvania and New York from coming into New England. The $1 billion Algonquin Incremental Market project, or AIM, is slated to go into service this November, pumping enough extra gas to heat 350,000 homes a day in southern New England.

Advertisement

How dependent each manufacturer is on natural gas for electricity varies, but Woodcock said it is an important issue for most across the state.

Other businesses, schools and hospitals also lauded the importance of a natural gas connection to the region during the construction of the $350 million Summit project in 2013 and 2014.

Madison Paper connected to the Summit natural gas line in April 2014 following six months of delay. The mill has been the anchor customer of the 68-mile steel backbone transmission pipeline in the Kennebec Valley that starts in Richmond and cuts north into Somerset County.

Lizzy Reinholt, a spokeswoman for Summit Natural Gas, said the loss of Madison Paper, one of the company’s major customers in central Maine, will affect Summit, though she would not say what the financial loss will be for the company.

“Summit Natural Gas of Maine made a substantial infrastructure investment to bring natural gas to the Madison Paper Mill and its closure will have a significant impact on us and the region,” Reinholt said in an email. “Now it’s time for all of us to work together and maintain the infrastructure that we’ve built so it’s there for future economic growth and opportunities.”

She said the company has plans to break ground on new construction areas in May.

Advertisement

In 2014 Sappi Fine Paper in Skowhegan, like Madison, also connected to the Summit natural gas pipeline, with officials at the time estimating a 30 percent reduction in energy costs from the connection, which is primarily used to operate the mill’s lime kiln. Burning natural gas provides a heat source for pulp chemical conversion and also can be used in one of the boilers to generate steam, according to Sappi spokeswoman Olga Karagiannis.

Karagiannis would not disclose how much money the natural gas connection has saved the mill but said it has reduced operating costs and CO2 emissions.

The mill is capable of generating 100 percent of its electrical needs on site with steam turbine generators, but also purchases electricity from ISO New England in various amounts. Depending on the time of year and production plans, Sappi also relies on biomass for its energy needs.

Yet like Drechsel, Karagiannis said it is important for Maine to complete the Energy Cost Reduction Act work.

“The pipeline capacity for natural gas directly affects the cost of natural gas for power generation,” Karagiannis said. “The gas cost determines the power cost. Every ratepayer in Maine and New England is affected, homeowners and businesses alike.”

VOLATILE COSTS

Advertisement

New England’s year of low-cost electricity in 2015 still leaves the region with the most expensive electricity in the contiguous United States, according to the U.S. Energy Information Administration.

“The volatility we saw last year in wholesale power prices — going from the third-highest monthly price in February to the lowest in June, and staying low through the rest of the year — illustrates the impact of natural gas pricing, and natural gas pipeline constraints, on the region’s power system,” said Gordon van Welie, president and CEO of ISO New England, in the statement last month.

“When the weather is mild and heating demand for natural gas is low, New England’s natural gas infrastructure has room to carry in the low-priced natural gas available on our doorstep.”

But when the winter is harsh and demand for gas heating is high, there isn’t enough natural gas pipeline in New England to fuel electricity generators.

When Madison Paper announced earlier this month that the company will be closing its doors in May, laying off 215 people, the mill cited as a top reason the decline in demand for supercalendered paper, the glossy magazine paper it makes.

But a few harsh winters such as the ones the region endured in 2014 and 2015 also factored into the mill’s demise, according to Drechsel, who compared high energy costs to pneumonia.

Advertisement

“They weakened us. So in 2016, when energy costs weren’t that bad because it was a mild winter, but we had (less) product demand and the low value of the Canadian dollar, we just couldn’t recover from that,” he said.

The company and others around Maine have called for an increase in pipeline capacity in New England to address the issue.

In 2013, Maine was one of the first states in New England to pass legislation aimed at expanding pipeline capacity with the Maine Energy Cost Reduction Act, which allowed the Public Utilities Commission to buy pipeline or order its electric companies to do so.

However, a study commissioned by the PUC last year found that it wasn’t cost-effective for state ratepayers to subsidize natural gas flow when Maine’s energy consumption makes up only about 9 percent of the overall energy consumption in New England.

Since then the legislation has stalled.

“If Maine assists in building pipeline capacity, those benefits don’t just go to Maine, because it’s a regional energy market,” said Woodcock, of the governor’s energy office.

Advertisement

He said states throughout New England are reviewing the possibility of adding pipeline in a cost-effective manner: “You want everybody to invest in this infrastructure, because the benefits are shared throughout the region.”

This story has been corrected.

Rachel Ohm — 612-2368

rohm@centralmaine.com

Twitter: @rachel_ohm

Copy the Story Link

Only subscribers are eligible to post comments. Please subscribe or login first for digital access. Here’s why.

Use the form below to reset your password. When you've submitted your account email, we will send an email with a reset code.